Step 1: Initial Consultation

Duration: 1-2 hours

We discuss your vision, requirements, site details, and budget. Share your ideas, sketches, inspiration images, must-haves and nice-to-haves. Information we need includes site address, soil test results, council requirements, bedroom and bathroom count, style preferences, and budget range.


Step 2: Concept Design

Duration: 1-2 weeks

We create 2-3 concept layouts based on your brief. You receive preliminary floor plans, basic elevations, and area calculations. Review, provide feedback, and we refine until you are happy with the direction.


Step 3: Design Development

Duration: 2-3 weeks

Your approved concept is developed into detailed design including floor plans with dimensions, full elevations, sections showing internal heights, window and door schedules, and material specifications.


Step 4: Structural Engineering

Duration: 2-3 weeks

Our engineers design the steel frame for your specific site including foundation design based on soil test, steel frame member sizing, connection details, wind zone compliance, BAL rating compliance if applicable, and full engineering certification.


Step 5: Documentation Package

Duration: 1-2 weeks

Complete drawing package prepared including council submission drawings, construction assembly drawings, engineering certification, and specifications.


Step 6: Manufacturing

Duration: 3-4 weeks

Your custom steel frame kit is manufactured with CNC cutting to exact specifications, pre-punched connection holes, component labelling, quality checking, and kit packaging.


Step 7: Delivery

Kit delivered to your site including all structural components, internal framing, fixings and fasteners, the structural engineering certification and assembly documentation. Roofing, cladding, windows and external doors are not part of the kit — you source those through your own local suppliers and licensed trades, who install them and issue the compliance certificates your permit needs.


Timeline Summary

Total: approximately 12-16 weeks from start to delivery

  • Consultation: Week 1
  • Concept design: Weeks 2-3
  • Design development: Weeks 4-6
  • Engineering: Weeks 7-9
  • Documentation: Weeks 10-11
  • Manufacturing: Weeks 12-15
  • Delivery: Week 16